What to Put in Writing With Every Subcontractor
October 15th, 2027
A subcontractor agreement does not need to be forty pages. It needs to answer the questions that come up when the work is late, the scope is disputed, or the invoice is higher than expected. Most of those questions have the same answer: it should have been in the contract.
The terms below are the minimum for an owner-builder. A simple written agreement with these sections is better than a detailed verbal understanding.
Scope of Work
Describe the work in enough detail that two people reading it would price the same job. Include the plans and specifications by reference and attach them. State what is included, and state what is excluded.
Exclusions matter as much as inclusions. A plumbing bid that excludes the water heater, the gas line, or the permit is not the same as one that includes them. A framing bid that excludes the crane, the dumpster, or the nails is not comparable. List the exclusions.
Price and Payment Schedule
State the total price and the payment schedule. Tie payments to completed milestones, not to dates. A deposit is normal for some trades, but a large payment before any work starts is a red flag.
Include the retainage if there is one. State how change orders affect the price. State whether the price includes tax, permits, equipment, and cleanup.
Schedule
Write down the start date, the number of working days, and the completion date. Define what counts as a weather day. State how delays are reported and whether the sub is entitled to additional time.
A schedule without consequences is a suggestion. Include a reasonable remedy for unexcused delay, and make sure the sub knows the next trade is scheduled behind them.
Change Orders
State that no change is performed without a written change order signed by the owner. Describe the form and the approval process. State that verbal changes are not binding.
This clause protects the sub as much as the owner. It prevents the owner from claiming a change was free and prevents the sub from claiming a change was approved when it was not.
Insurance and Licenses
Require a certificate of insurance showing general liability and workers' compensation, with limits that match the project. Require the sub to name the owner as an additional insured where appropriate. Verify the license or registration required by the trade and the jurisdiction.
Keep the certificate in the project file and check the expiration date. An expired policy is the same as no policy.
Lien Waivers
Require a signed lien waiver with each payment. The waiver confirms that the sub and its suppliers have been paid for the work covered by that payment. In Texas, unpaid subs and suppliers can file liens against the property, and the owner needs the waivers to protect the title.
State the form of the waiver and the timing. Make it a condition of payment, not an afterthought.
Warranty
State the warranty period for labor and materials, what it covers, and how a claim is made. Most trades warrant their work for a year, and manufacturers warrant materials for longer. Require the sub to pass through manufacturer warranties and provide the documentation.
Cleanup and Site Rules
State who removes debris, who provides the dumpster, and what condition the site should be left in each day. Include rules for parking, smoking, music, restroom use, and access. Include a requirement to protect finished surfaces and other trades' work.
Termination and Disputes
State the grounds for termination, the notice required, and how the owner pays for work completed. State the dispute process: written notice, a cure period, and mediation or arbitration if the contract requires it.
A termination clause that is clear protects the owner when a sub walks off the job and protects the sub when the owner stops paying.
Red Flags in a Subcontractor Agreement
- No written scope, only a verbal quote
- A large deposit before any work
- No insurance certificate
- No lien waiver requirement
- No schedule or completion date
- Payment due before inspection or completion
- A contract that the owner cannot understand
Owner Builder Network provides contract guidance and a network of trades who work with owner-builders as part of the owner builder program. The home building process page shows where contracts and bid packages fit, and the benefits of the program page explains the support available at each tier.
Put the scope, the price, the schedule, and the waivers in writing. The conversation on site is easier when the contract already answered the question.