Utilities are invisible in the finished house and decisive in the schedule. A missing water tap, a delayed meter, or a septic permit that has not been issued can stop the foundation, the drywall, or the final inspection. The work of connecting a new home to water, sewer, power, gas, and internet starts long before the first trench is dug.

The owner-builder is responsible for arranging most of these services. The city or county, the utility, and the trades each play a part, and the sequence matters.

Start With Availability

Before buying land or finalizing a plan, confirm that each utility can serve the site. Ask for written availability, not a verbal yes. The answers determine cost and sometimes whether the lot can be built on at all.

  • Water: municipal service, a water supply corporation, or a private well
  • Sewer: municipal sewer, a community system, or an on-site septic system
  • Electric: the transmission and distribution utility that serves the area
  • Gas: natural gas or propane
  • Internet: fiber, cable, fixed wireless, or satellite

Water

If municipal water is available, the owner pays a tap fee and the utility installs a meter. The plumber runs the service line from the meter to the house. The trench, the meter box, and the backflow prevention requirements vary by jurisdiction.

If the lot is outside a water system, a well is required. The well needs a permit, a pump, a pressure tank, and a water test. Well drillers can be booked weeks out, so schedule early. Water quality may require treatment for hardness, iron, or sulfur.

Sewer and Septic

A municipal sewer connection requires a tap, a lateral line, and an inspection. In some cities the owner pays the tap fee and a licensed plumber makes the connection. Confirm the depth and the location of the city main before the site work begins.

Outside a sewer service area, an on-site sewage facility is required. In Texas, septic systems are permitted through the county or the state, and the design depends on the soil and the size of the house. The site evaluation and permit can take weeks. Do not start the foundation before the septic design is approved and the location is marked.

Electric Service

Most of Texas has a competitive retail electric market. The wires are owned by a transmission and distribution utility, and the customer chooses a retail provider. The builder or owner applies for service, the utility designs the connection, and a licensed electrician installs the meter loop and the service entrance.

Temporary power is usually the first electric connection on a new site. A temporary pole with a meter and a panel gives the trades power for tools and lights. Apply for temporary service early, because the utility may need to set a pole or extend a line.

Permanent service follows the final electrical inspection. The meter is set, the account is transferred, and the house is energized.

Gas

If natural gas is available, the gas utility or a licensed plumber runs the service line and sets the meter. If gas is not available, a propane tank is installed, usually underground or at the side of the house, with a provider who fills it on a schedule.

Gas appliances need proper venting and combustion air. The mechanical contractor and the plumber coordinate the connections, and the inspection happens before the appliances are fired.

Internet and Low Voltage

Internet is the utility most often overlooked. Confirm which providers serve the address and what speed they can deliver. If fiber is not available, plan for the best alternative. Run conduit from the utility entry point to the low-voltage panel during construction, even if the service is installed later.

The same conduit path can carry cable, security, and future fiber. It is cheap to install before the walls close and expensive afterward.

Permits and Inspections

Utility connections require permits and inspections in most jurisdictions. Water and sewer taps are inspected by the city. Electrical service is inspected before the meter is set. Septic systems are inspected by the county or the state. Gas lines are pressure-tested and inspected.

Keep the permits and inspection reports in the project file. The final certificate of occupancy depends on them.

Sequence and Cost

The practical order is availability, applications, site work, temporary power, underground lines, foundation, rough-in, inspections, meters, and final connections. Costs include tap fees, impact fees, meter fees, trenching, conduit, and the utility's extension charges.

Get written estimates for every connection before the budget is final. Utility costs are one of the most common surprises in a first build.

Owner Builder Network reviews utility availability during the home building process and helps families build the connection costs into the budget. Our build on your own land guidance covers rural sites where wells and septic are part of the plan.

Call the utilities before you call the excavator. The connections take longer than the trench, and the house cannot close without them.