Change Orders: Price and Approve Them Before Work Starts

May 15th, 2027

Two people signing and reviewing paperwork at a desk.

A change order is not a failure. Houses change, and some changes are worth the money. The problem is the change that happens without a price, a schedule, or a signature. Those are the ones that show up as a surprise invoice in month eight and a dispute in month ten.

The rule for owner-builders is simple: no work starts on a change until the change is written down, priced, and signed. Every trade should hear that rule before the first day on site.

What Counts as a Change

A change is any work that differs from the signed contract scope or the approved plans. That includes:

  • Adding or removing a room, wall, door, or window
  • Changing a material, fixture, or finish after selection
  • Moving plumbing, electrical, or HVAC after rough-in
  • Upgrading equipment or appliances
  • Fixing damage caused by another trade
  • Changing the schedule in a way that costs someone money

Some items are not changes. A contractor correcting defective work is not a change order, and neither is work required by code that was missed in the bid. Those are the contractor's responsibility, and they should be resolved under the original contract.

Why Verbal Changes Fail

A verbal agreement feels efficient on site. It also has no price, no date, and no record. When the invoice arrives, the owner remembers a different conversation. When the work is wrong, the sub says the owner asked for it.

Text messages and emails are better than nothing, but they are not a change order. Use the written form even when the change is small. The habit protects both sides.

The Anatomy of a Good Change Order

A complete change order includes:

  • A number and date
  • The subcontractor and the original contract reference
  • A clear description of the change
  • The reason for the change
  • The added or subtracted cost, broken down if possible
  • The schedule impact in working days
  • Whether the change needs lender approval
  • Signature lines for the owner and the subcontractor

One page is enough. The point is that the document exists before the work begins.

How to Price a Change

Ask for a breakdown when the number feels high. A change order should cover material, labor, and any real overhead. It should not include work already covered by the original contract. If a sub is adding a markup on a change, ask what the markup covers.

Compare the change price to the original bid line. If the change removes work, the credit should be proportional. Owners often accept a high charge for an addition and a small credit for a deletion, and the gap adds up.

Schedule Impact

Every change should state how many days it adds or removes. A change that costs five hundred dollars but delays the cabinets by two weeks is not a five-hundred-dollar decision. The schedule impact is part of the price.

If the change happens after rough-in, expect longer delays and higher costs. Moving a wall after electrical, plumbing, and drywall are complete is a different project from moving it on paper.

Lender Approval

Most construction lenders require approval for changes that affect the budget or the plans. Some allow small changes within the contingency line and require a formal amendment above a threshold. Ask your loan officer for the rule at closing, not when the change appears.

Keep the approved change order with the draw package. A lender who sees a budget change without documentation will hold the draw.

Keep a Change Log

A change log is a simple spreadsheet: number, date, description, amount, schedule impact, and status. Update it the same day the change order is signed. At any point, the log answers the two questions every owner-builder asks: how much have we changed, and how far has the schedule moved?

How to Avoid Most Changes

  • Make finish selections before construction starts.
  • Have the plan reviewed by the trades who will build it.
  • Walk the framing with the electrician, plumber, and HVAC contractor before rough-in.
  • Decide on fixtures and appliances before the rough-in is complete.
  • Do not visit the site with a new idea and a tape measure.

Owner Builder Network helps families set up a change order process at the start of the home building process. Our owner builder program also reviews changes for cost and schedule impact, which is one of the quieter benefits of the program.

Every change costs less before it is built. Write it, price it, sign it, then build it.